STATUS

(1 / 1)


 							STUN RUNNER
							STUN RUNNER
                    GAME DEVELOPMENT STATUS             STUN RUNNER
   
DATE: FEB 3, 89			
                        PL: MIKE HALLY          DATE STARTED: 28 APR 88								9  JUN 88     PROJECT LEADER: HALLY	START DATE:  2 MAY 88					
LAB: STUN RUNNER          (MULTISYNC)
EXT: 1727 OR 1720      	NUMBER  : 511
                          TEAM NU           

|		  	| SCHEDULE or |  MISSED DATES 			|
|			|  |					|
------------------------------------------------------------------------
  PROJECT START:	 < 2 MAY 88>
  1ST REVIEW:	 	 < 6 JUL 88>	8 JUL 88
  MULTISYNC PCB DEBUGGED < 1 AUG 88> 
  2ND REVIEW:	         < 2 SEP 88>   24 AUG 88    15 AUG 88 	 
  3RD REVIEW:	        < 10 NOV 88>    4 NOV 88    14 OCT 88 
  FOCUS GROUP:          < 22 NOV 88>   16 NOV 88
  4TH REVIEW:  **	  10 FEB 89    20 JAN 89    13 JAN 89     
  FIELD TEST:		  24 FEB 89    10 FEB 89
  PROD RELEASE:		  19 APR 89 
  FGA:			   4 JUN 89 
    
  ACTION ITEMS:
   1. HARDWARE- USING NEW SAD AUDIO BOARD.
   2. WE DECIDED TO GO WITH A STANDARD RES. MONITOR (512 x 240)
      OF THE 19" VARIETY.
   3. A NEW UP TO DATE COST OF THE STUN GAME IS AVAILABLE. 
   4. THE ABILITY OF SPEED CONTROL IS STILL AN OUTSTANDING 
      ISSUE. MAYBE AFTER OUR 4 TH. REVIEW WE WILL MAKE A DECISION
      FOR FIELD TEST. (LOOKS LIKE THE FLIGHT CONTROL IS BACK)
   5. WE WILL BE USING THE FAMILY CABINET FOR FIELD TEST.
   6. ADDITIONAL ANIMATION FOR FIELD TEST REQUIRED AFTER REVIEW.
   7. 4 TH. REVIEW PUSHED BACK ANOTHER WEEK TO 2/10/89. THE TEAM
      HAS BEEN SICK AND NEEDS THE TIME TO TEST OUT NEW ADDITIONS.
   8. A DETAILED WRITE-UP OF GAME GOAL STILL NEEDS TO BE DONE.
   9. THE NEW EDITOR SHOULD ALLOW FOR QUICK TUNNEL DESIGN!
  10. VOICE FOR FIELD TEST RECORDED ON 1/17/89. ITS IN GAME.
  11. ED IS JUST WORKIN......."I BE WORKIN BOSS, MY LATEST
      CREATION IS THE ABILITY TO VERTICALLY SCROLL BACKGROUND"
Message 1 of 1

Feb 02, 1989