(1 / 1)
Date: February 02, 1989 13:46
From: ERNIE::HALLY
To: @[HALLY]STUN
STUN RUNNER STUN RUNNER GAME DEVELOPMENT STATUS STUN RUNNER DATE: FEB 3, 89 PL: MIKE HALLY DATE STARTED: 28 APR 88 9 JUN 88 PROJECT LEADER: HALLY START DATE: 2 MAY 88 LAB: STUN RUNNER (MULTISYNC) EXT: 1727 OR 1720 NUMBER : 511 TEAM NU | | SCHEDULE or | MISSED DATES | | || | ------------------------------------------------------------------------ PROJECT START: < 2 MAY 88> 1ST REVIEW: < 6 JUL 88> 8 JUL 88 MULTISYNC PCB DEBUGGED < 1 AUG 88> 2ND REVIEW: < 2 SEP 88> 24 AUG 88 15 AUG 88 3RD REVIEW: < 10 NOV 88> 4 NOV 88 14 OCT 88 FOCUS GROUP: < 22 NOV 88> 16 NOV 88 4TH REVIEW: ** 10 FEB 89 20 JAN 89 13 JAN 89 FIELD TEST: 24 FEB 89 10 FEB 89 PROD RELEASE: 19 APR 89 FGA: 4 JUN 89 ACTION ITEMS: 1. HARDWARE- USING NEW SAD AUDIO BOARD. 2. WE DECIDED TO GO WITH A STANDARD RES. MONITOR (512 x 240) OF THE 19" VARIETY. 3. A NEW UP TO DATE COST OF THE STUN GAME IS AVAILABLE. 4. THE ABILITY OF SPEED CONTROL IS STILL AN OUTSTANDING ISSUE. MAYBE AFTER OUR 4 TH. REVIEW WE WILL MAKE A DECISION FOR FIELD TEST. (LOOKS LIKE THE FLIGHT CONTROL IS BACK) 5. WE WILL BE USING THE FAMILY CABINET FOR FIELD TEST. 6. ADDITIONAL ANIMATION FOR FIELD TEST REQUIRED AFTER REVIEW. 7. 4 TH. REVIEW PUSHED BACK ANOTHER WEEK TO 2/10/89. THE TEAM HAS BEEN SICK AND NEEDS THE TIME TO TEST OUT NEW ADDITIONS. 8. A DETAILED WRITE-UP OF GAME GOAL STILL NEEDS TO BE DONE. 9. THE NEW EDITOR SHOULD ALLOW FOR QUICK TUNNEL DESIGN! 10. VOICE FOR FIELD TEST RECORDED ON 1/17/89. ITS IN GAME. 11. ED IS JUST WORKIN......."I BE WORKIN BOSS, MY LATEST CREATION IS THE ABILITY TO VERTICALLY SCROLL BACKGROUND"
Feb 02, 1989