(1 / 1)
Date: January 26, 1989 14:04
From: GAWD::HALLY
To: @[HALLY]STUN
STUN RUNNER STUN RUNNER GAME DEVELOPMENT STATUS STUN RUNNER DATE: JAN 27, 89 PL: MIKE HALLY DATE STARTED: 28 APR 88 9 JUN 88 PROJECT LEADER: HALLY START DATE: 2 MAY 88 LAB: STUN RUNNER (MULTISYNC) EXT: 1727 OR 1720 NUMBER : 511 TEAM NU | | SCHEDULE or | MISSED DATES | | || | ------------------------------------------------------------------------ PROJECT START: < 2 MAY 88> 1ST REVIEW: < 6 JUL 88> 8 JUL 88 MULTISYNC PCB DEBUGGED < 1 AUG 88> 2ND REVIEW: < 2 SEP 88> 24 AUG 88 15 AUG 88 3RD REVIEW: < 10 NOV 88> 4 NOV 88 14 OCT 88 FOCUS GROUP: < 22 NOV 88> 16 NOV 88 4TH REVIEW: ** 10 FEB 89 20 JAN 89 13 JAN 89 FIELD TEST: 24 FEB 89 10 FEB 89 PROD RELEASE: 19 APR 89 FGA: 4 JUN 89 ACTION ITEMS: 1. HARDWARE- NEW SAD AUDIO BOARDS IN-HOUSE. NOT USING YET. 2. WE DECIDED TO GO WITH A STANDARD RES. MONITOR (512 x 240) OF THE 19" VARIETY. 3. A NEW UP TO DATE COST OF THE STUN GAME IS AVAILABLE. 4. THE ISSUE OF THE GAME CONTROLS IS STILL AN OUTSTANDING ISSUE. MAYBE AFTER OUR 4 TH. REVIEW WE WILL MAKE A DECISION FOR FIELD TEST. (LOOKS LIKE THE FLIGHT CONTROL IS BACK) 5. WE WILL BE USING THE FAMILY CABINET FOR FIELD TEST. 6. ADDITIONAL ANIMATION FOR FIELD TEST REQUIRED AFTER REVIEW. 7. 4 TH. REVIEW PUSHED BACK ANOTHER WEEK TO 2/10/89. THE TEAM HAS BEEN SICK BUT PLANS TO KICK ASS AND TAKE NAMES SOON. 8. A DETAILED WRITE-UP OF GAME GOAL IS BEING WRITTEN. 9. THE NEW EDITOR SHOULD ALLOW FOR QUICK TUNNEL DESIGN! 10. VOICE FOR FIELD TEST RECORDED ON 1/17/89. 11. ED IS JUST WORKIN......."I BE WORKIN BOSS, MY LATEST CREATION IS THE ABILITY TO VERTICALLY SCROLL BACKGROUND"
Jan 26, 1989