Date: February 02, 1988 15:41
From: SANDY::PAAUW
To: MARGOLIN,MONCRIEF,DOWNEND,VANELDREN,PAAUW
The TWIG files have been transferred to National's mainframe for pre- route simulation, which should match the simulation results from the Mentor workstation. The first attempt failed 2/1/88 and the National engineer is currently massaging the files. I don't expect any major problems and still expect mask release about Feb. 15 and protos in mid-March. The steps remaining before mask release are pre-route simulation, fault grading (one pass, gratis), place & route, post-route simulation. -- Don
Feb 02, 1988