Date: December 07, 1989 14:43
From: CHARM::ROTBERG
To: @STATUS
STUN RUNNER
STUN RUNNER
GAME DEVELOPMENT STATUS STUN RUNNER
DATE: DECEMBER 7, 1989
PL: ED ROTBERG DATE STARTED: 28 APR 88 9 JUN 88 PROJECT LEADER: HALLY START DATE: 2 MAY 88
LAB: STUN RUNNER (MULTISYNC)
EXT: 1727 OR 1720 NUMBER : 511
TEAM NU
| | SCHEDULE or | MISSED DATES |
| | | |
------------------------------------------------------------------------
PROJECT START: < 2 MAY 88>
1ST REVIEW: < 6 JUL 88> 8 JUL 88
MULTISYNC PCB DEBUGGED < 1 AUG 88>
2ND REVIEW: < 2 SEP 88> 24 AUG 88 15 AUG 88
3RD REVIEW: < 10 NOV 88> 4 NOV 88 14 OCT 88
FOCUS GROUP: < 22 NOV 88> 16 NOV 88
4TH REVIEW: < 31 MAR 89> 20 JAN 89 13 JAN 89
FIELD TEST: < 14 APR 89> 7 APR 89 10 MAR 89
FIELD TEST #2: < 16 JUN 89>
FIELD TEST #3: < 7 JUL 89>
PROD RELEASE: < 4 AUG 89> 28 JUL 89 2 JUN 89 26 MAY 89
FGA: < 18 SEP 89> 25 SEP 89 15 SEP 89 21 JUL 89
An IBM PC Clone has been brought into the STUN lab so that the installation
of the Japanese fonts can be done. Mary Fujihara has informed that the
translations of the agreed upon text has also been done, but it will need to
be edited into a Macintosh for inclusion into the program.
Anne Hayes has given us a spec for a Taiwanese chasis and color monitor that
Entropy Intl. wants to use with a STUN Runner kit (didn't know there was such
a beast!!). THis has been forward first to Jed, and then to Rick Meyette to
determine if our kit (??) will drive their equipment. I have no further
information on the status of this at this time.
Dec 07, 1989