(1 / 1)
Date: December 07, 1989 14:43
From: CHARM::ROTBERG
To: @STATUS
STUN RUNNER STUN RUNNER GAME DEVELOPMENT STATUS STUN RUNNER DATE: DECEMBER 7, 1989 PL: ED ROTBERG DATE STARTED: 28 APR 88 9 JUN 88 PROJECT LEADER: HALLY START DATE: 2 MAY 88 LAB: STUN RUNNER (MULTISYNC) EXT: 1727 OR 1720 NUMBER : 511 TEAM NU | | SCHEDULE or | MISSED DATES | | || | ------------------------------------------------------------------------ PROJECT START: < 2 MAY 88> 1ST REVIEW: < 6 JUL 88> 8 JUL 88 MULTISYNC PCB DEBUGGED < 1 AUG 88> 2ND REVIEW: < 2 SEP 88> 24 AUG 88 15 AUG 88 3RD REVIEW: < 10 NOV 88> 4 NOV 88 14 OCT 88 FOCUS GROUP: < 22 NOV 88> 16 NOV 88 4TH REVIEW: < 31 MAR 89> 20 JAN 89 13 JAN 89 FIELD TEST: < 14 APR 89> 7 APR 89 10 MAR 89 FIELD TEST #2: < 16 JUN 89> FIELD TEST #3: < 7 JUL 89> PROD RELEASE: < 4 AUG 89> 28 JUL 89 2 JUN 89 26 MAY 89 FGA: < 18 SEP 89> 25 SEP 89 15 SEP 89 21 JUL 89 An IBM PC Clone has been brought into the STUN lab so that the installation of the Japanese fonts can be done. Mary Fujihara has informed that the translations of the agreed upon text has also been done, but it will need to be edited into a Macintosh for inclusion into the program. Anne Hayes has given us a spec for a Taiwanese chasis and color monitor that Entropy Intl. wants to use with a STUN Runner kit (didn't know there was such a beast!!). THis has been forward first to Jed, and then to Rick Meyette to determine if our kit (??) will drive their equipment. I have no further information on the status of this at this time.
Dec 07, 1989