(1 / 1)
Date: May 18, 1989 15:36
From: CHARM::ROTBERG
To: @STATUS
STUN RUNNER STUN RUNNER GAME DEVELOPMENT STATUS STUN RUNNER DATE: MAY 18, 1989 PL: ED ROTBERG DATE STARTED: 28 APR 88 9 JUN 88 PROJECT LEADER: HALLY START DATE: 2 MAY 88 LAB: STUN RUNNER (MULTISYNC) EXT: 1727 OR 1720 NUMBER : 511 TEAM NU | | SCHEDULE or | MISSED DATES | | || | ------------------------------------------------------------------------ PROJECT START: < 2 MAY 88> 1ST REVIEW: < 6 JUL 88> 8 JUL 88 MULTISYNC PCB DEBUGGED < 1 AUG 88> 2ND REVIEW: < 2 SEP 88> 24 AUG 88 15 AUG 88 3RD REVIEW: < 10 NOV 88> 4 NOV 88 14 OCT 88 FOCUS GROUP: < 22 NOV 88> 16 NOV 88 4TH REVIEW: < 31 MAR 89> 20 JAN 89 13 JAN 89 FIELD TEST: < 14 APR 89> 7 APR 89 10 MAR 89 PROD RELEASE: 2 JUN 89 26 MAY 89 19 APR 89 FGA: 21 JUL 89 14 JUL 89 4 JUN 89 Another wrench has been thrown into the control issue. A "new" Slider control was tested, and many feel it is clearly the superior control. By the same token, many feel that it is seriously worse, not better. We are planning on Focus testing the two controllers with the hope of getting some unbiased feedback on this issue. The ADSP II board has been delivered, stuffed, and is being tested. Graphics developement continues. We have a new Map screen, and are trying to speed up the decompression routine in order to make it fit seamlessly. Software development continues. Unfortunately so much time has been spent on things like the cabinet and the controller issues that we are falling behind on the tunnel design.
May 18, 1989