STUN RUNNER
GAME DEVELOPMENT STATUS STUN RUNNER
DATE: JAN 13, 89
PL: MIKE HALLY DATE STARTED: 28 APR 88 9 JUN 88 PROJECT LEADER: HALLY START DATE: 2 MAY 88
LAB: STUN RUNNER (MULTISYNC)
EXT: 1727 OR 1720 NUMBER : 571
TEAM NU
| | SCHEDULE or | MISSED DATES |
| | | |
------------------------------------------------------------------------
PROJECT START: < 2 MAY 88>
1ST REVIEW: < 6 JUL 88> 8 JUL 88
MULTISYNC PCB DEBUGGED < 1 AUG 88>
2ND REVIEW: < 2 SEP 88> 24 AUG 88 15 AUG 88
3RD REVIEW: < 10 NOV 88> 4 NOV 88 14 OCT 88
FOCUS GROUP: < 22 NOV 88> 16 NOV 88
4TH REVIEW: 20 JAN 89 13 JAN 89
FIELD TEST: * 10 FEB 89 * MAY SLIP OUT A WEEK OR SO!!!!
PROD RELEASE: 19 APR 89
FGA: 4 JUN 89
ACTION ITEMS:
1. HAD HARDWARE MEETING WITH STUN/DRIVER GROUP. DECIDED TO KEEP
MAIN AND ADSP BOARDS THE SAME. (STUN WILL STUFF LESS PARTS)
DETAILED COST SHEET AVAILABLE UPON REQUEST.
2. WE DECIDED TO GO WITH A STANDARD RES. MONITOR. (512 x 240)
MONITOR SIZE IS STILL A BIG QUESTION TO BE SORTED OUT.
WE WILL DO A SIDE BY SIDE COMPARISON OF 19 VS. 25 ON 1/12/89.
3. A NEW UP TO DATE PROJECTION OF THE STUN GAME COST IS
AVAILABLE UPON REQUEST.
4. THE ISSUE OF THE GAME CONTROLS IS STILL AN OUTSTANDING
ISSUE WHICH MUST BE ADDRESSED ASAP. A HI-LOW SPEED SHIFTER
IS GOING TO BE TRIED WITH A HALL-EFFECT JOYSTICK.(ASSAULT GRIP)
THIS CONTROL SET-UP WILL BE READY ON 1/12/89 TO TRY OUT.
5. MIKE JANG IS STARTING AN UPRIGHT CABINET CONCEPT BUT MONITOR
ISSUE NEEDS TO BE DECIDED ON. (SEE #2 ABOVE)
6. ADDITIONAL ANIMATION FOR FIELD TEST IN PROGRESS.
7. 4 TH. REVIEW PUSHED BACK ONE WEEK TO 1/20/89.
8. A DETAILED WRITE-UP OF GAME GOAL HAS BEEN WRITTEN AND IS AVAIL.
9. ANDY HAS COMPLETED A NEW EDITOR FOR ME. (MANY THANKS)!
10. HELD VOICE CUE MEETING ON 1/10/89.
11. ED IS JUST WORKIN......."I BE WORKIN BOSS"
Jan 12, 1989