(1 / 1)
Date: January 12, 1989 11:36
From: GAWD::HALLY
To: @[HALLY]STUN
STUN RUNNER STUN RUNNER GAME DEVELOPMENT STATUS STUN RUNNER DATE: JAN 13, 89 PL: MIKE HALLY DATE STARTED: 28 APR 88 9 JUN 88 PROJECT LEADER: HALLY START DATE: 2 MAY 88 LAB: STUN RUNNER (MULTISYNC) EXT: 1727 OR 1720 NUMBER : 571 TEAM NU | | SCHEDULE or | MISSED DATES | | || | ------------------------------------------------------------------------ PROJECT START: < 2 MAY 88> 1ST REVIEW: < 6 JUL 88> 8 JUL 88 MULTISYNC PCB DEBUGGED < 1 AUG 88> 2ND REVIEW: < 2 SEP 88> 24 AUG 88 15 AUG 88 3RD REVIEW: < 10 NOV 88> 4 NOV 88 14 OCT 88 FOCUS GROUP: < 22 NOV 88> 16 NOV 88 4TH REVIEW: 20 JAN 89 13 JAN 89 FIELD TEST: * 10 FEB 89 * MAY SLIP OUT A WEEK OR SO!!!! PROD RELEASE: 19 APR 89 FGA: 4 JUN 89 ACTION ITEMS: 1. HAD HARDWARE MEETING WITH STUN/DRIVER GROUP. DECIDED TO KEEP MAIN AND ADSP BOARDS THE SAME. (STUN WILL STUFF LESS PARTS) DETAILED COST SHEET AVAILABLE UPON REQUEST. 2. WE DECIDED TO GO WITH A STANDARD RES. MONITOR. (512 x 240) MONITOR SIZE IS STILL A BIG QUESTION TO BE SORTED OUT. WE WILL DO A SIDE BY SIDE COMPARISON OF 19 VS. 25 ON 1/12/89. 3. A NEW UP TO DATE PROJECTION OF THE STUN GAME COST IS AVAILABLE UPON REQUEST. 4. THE ISSUE OF THE GAME CONTROLS IS STILL AN OUTSTANDING ISSUE WHICH MUST BE ADDRESSED ASAP. A HI-LOW SPEED SHIFTER IS GOING TO BE TRIED WITH A HALL-EFFECT JOYSTICK.(ASSAULT GRIP) THIS CONTROL SET-UP WILL BE READY ON 1/12/89 TO TRY OUT. 5. MIKE JANG IS STARTING AN UPRIGHT CABINET CONCEPT BUT MONITOR ISSUE NEEDS TO BE DECIDED ON. (SEE #2 ABOVE) 6. ADDITIONAL ANIMATION FOR FIELD TEST IN PROGRESS. 7. 4 TH. REVIEW PUSHED BACK ONE WEEK TO 1/20/89. 8. A DETAILED WRITE-UP OF GAME GOAL HAS BEEN WRITTEN AND IS AVAIL. 9. ANDY HAS COMPLETED A NEW EDITOR FOR ME. (MANY THANKS)! 10. HELD VOICE CUE MEETING ON 1/10/89. 11. ED IS JUST WORKIN......."I BE WORKIN BOSS"
Jan 12, 1989