There is a scheduling problem with the Scidesign schematic entry stations: 
Not enough stations for current projects.
Here are the Projects that I know of:

SAC Audio board. McCarthy et al. Field testing with Cyberball and 
				Escape... April/May/June.
Cyberball.	Snyder. Field testing April/May.
War.		Stempler. For two projects, War and Quarterdeck.
MOB.		McCarthy. New Motion Object chip development (schematics only).
Blitter.	Snyder. New Motion Object technology

We need to get together briefly to decide on some time allocation scheme to 
take care of these projects. If you know that you will not need a station 
at any particular period, please reply now so that we can see how big the 
conflict really is.

It there are any more projects requiring Schematic entry time this month 
please relpy to me also.

							Pat.
Message 1 of 1

Mar 07, 1988