Date: June 27, 1989 10:27
From: KIM::RAY
To: ROTBERG,STUN,CAMERON,MARGOLIN,FYI::TAKAICHI,RAY
Rich has asked us to put together a list of long-lead ( > 6wks ) parts for STUN Runner. Carole is working on the cabinet, controls, etc. Jed -- can you mark up Rick's list of Hard Drivin's long-lead or common parts with STUN? Please have these lists (with cost estimates) to me by Thursday. Ed -- Rich also reminded me that your program must use SLAPSTICK so customers cannot convert a Hard Drivin' Multisync to a STUN Multisync. It should be in a socket. This needs to be done before the first game is shipped to a customer (pre-prod?). Thanks!! John
(2 / 4)
Date: June 27, 1989 15:13
From: KIM::MARGOLIN
To: MARGOLIN,MARGOLIN
1 of 2
To: John Ray
Fr: Jed Margolin
Re: STUN RUNNER Parts that are common with Compact Hard Drivin'
Dt: 6/27/89
ADSP II
-------
We have ECNed Hard Drivin' and Compact Hard Drivin' to use ADSP II
on the next buy. Therefore, ADSP II is common to Hard Drivin', Compact
Hard Drivin', and Stun Runner. (Stun Runner will presumably make use of
the two extra ROM sockets.)
MultiSync Board
---------------
1. Stun Runner uses a 40 MHz oscillator module at XOSC4 instead of the
32 MHz unit that Compact Hard Drivin' uses. Oscillator modules frequently
require several weeks' lead time.
2. To reduce costs the Timekeeper will be replaced with another ZeroPower RAM.
3. Slapstik 17 was reserved for Hard Drivin' but not used. I assume it is
available for Stun Runner.
4. There are several parts that Compact Hard Drivin' uses that Stun Runner
does not.
The following are not used on Stun Runner
5 137540-150 1 IC, 48T02-15, RAM 200E
8 137543-001 1 IC, 68681 200A
46 137580-001 1 IC, 4066B 205B
47 137546-003 4 IC, 4464, 64K X 4, DRAM 5K,15K,25K,35K
83 136068-1135 1 IC, PROM, 82S123 195U
84 137403-001 1 IC, MC1488 210A
85 137263-001 1 IC, MC1489AL 210B
89 137614-001 1 IC, AD711KN 15B
136 144000-011 1 XTAL, 3.6864, STANDUP XTAL1
138 144008-005 1 XTAL, 50 MHZ, OSCILLATOR XOSC3
miscellaneous other ICs, connectors, resistors, and capacitors
2 of 2
5. There are a few parts that Stun Runner uses that Compact Hard Drivin'
does not. They are:
137526-001 1 IC, SCUM 175W
137484-001 1 IC, AS08 175T
137134-001 1 IC, 74LS245 175R
144008-004 1 Oscillator, 40 MHz XOSC4
137412-117 1 Slapstic 17 200K
6. Parts with changes in quantities:
137538-002 IC, 34010-50 Uses One instead of Two
179237-068 SOCKET, 68 PIN Uses Two instead of Three
137442-150 IC, 48Z02-15, RAM Uses Two instead of One
I need Ed to tell me that the special board I had made up for him works, so
I can give Art the schematic, so we can get an official Stun Runner parts list.
Jed
(3 / 4)
Date: July 06, 1989 16:59
From: KIM::MARGOLIN
To: RAY,ROTBERG,CAMERON,MARGOLIN
Stun Runner ----------- Last week I gave Art the inputs for Stun MultiSync, which requires marking the schematics to show what is loaded on the board and doing the parts list. It does not involve any PC layout changes. We have been bumped from the schedule by a job they are doing for Tengen. I have not been given a reschedule date. ADSP II ------- The parts list for the Stun Runner version of ADSP II is ready to be signed off. This assumes you want all six graphics ROMs stuffed. Jed
(4 / 4)
Date: July 07, 1989 14:49
From: CHARM::ROTBERG
To: KIM::MARGOLIN
Jed, Yep, we want (read as NEED) all 6 roms. Thanks -- will sign it off on Monday. Ed