This is an important week. We have to get another Steel Talons cabinet
functional for the FCC test scheduled for the week of 6/3. If the FCC test
slips, it is possible that the Doc release on 6/17 will slip too.
Pete's group is building up the cabinet and will supply everything but
the PCB's.
Glen/Erik need to supply the PCB's:
Glen: (2) Multi-sync with all mods including SLOOP and SCOM interrupt.
Mods have to be extra neat and close to PCB.
(2) SA2S
(1) Rump Thump
Glen: please see Stevie and see if she needs any PCB's to
assist in the harness layout; I gave her (2) Multi-
Syncs and (1) SA2S PCB.
ERIK: (2) DSIII (if we have to, we can take them from Lipson's bench)
(2) DSPCOM (Lipson has DSPLINKS - no good: Need DSPCOM w/ASIC 65)
PROBLEM: Erik Durfey and Rick Moncrief are on VACATION all week.
Can Jed supply the needed PCB's?
PROBLEM: Ed & Ed's bench setup is still running DSPLINK PCB's - is firmware
compatible between DSPCOM and DSPLINK?
PROBLEM: Controls may not arrive til Thursday - then Jerry's group has to
construct them.
Let's try to get the game (cabinet is currently in Harness area) running by
6/3/91 at 5 PM even though the odds look low right now.